The ČEPS Control Centre performs a regular technical assessment of the Czech transmission system (TS) and the overall operation of the Czech power system (PS).
The following parameter values are assessed in particular:
-
Frequency;
-
ACE (Area Control Error);
-
Generation (gross);
-
Balance within the TS and PS;
-
Load (gross);
-
Planned and unplanned transfers;
-
Power from AnS activation.
Power balance plans are prepared and operations-related risks as well as network and power plant failures are assessed.
The most important data relating to the above parameters is available in the For Partners – All Data section.